Location: Noginsk District, Industrial Park “Park Noginsk”
Total area: 40,000 m2
Construction period: 2008-2009
Completed works: customer functions, construction.
ПРОИЗВОДСТВЕННО-СКЛАДСКОЙ КОМПЛЕКС ЗАО "КВИК-МИКС"
Location: Noginsk District, Industrial Park “Park Noginsk”
Total area: 12,000 m2
Construction period: 2008-2009
Completed works: customer functions, designing, construction.
АДМИНИСТРАТИВНО-ХОЗЯЙСТВЕННЫЙ КОМПЛЕКС ООО "ПАРК НОГИНСК"
Location: Noginsk District, Industrial Park “Park Noginsk”
Total area: 1 000 m2
Construction period: 2008-2009
Completed works: customer functions, designing, construction.
ГИПЕРМАРКЕТ ТОРГОВОЙ СЕТИ "СТРОЙДЕПО"
Location: Noginsk District, Industrial Park “Park Noginsk”
Total area: 6,000 m2
Construction period: 2007-2008
Completed works: designing, constructio
ПОЛИГРАФИЧЕСКИЙ КОМПЛЕКС "ПУШКИНСКАЯ ПЛОЩАДЬ"
Location: Moscow, Pechatniki district
Total area: 45,000 m2
Construction period: 2002-2008
Completed works: designing, construction.
ОФИСНЫЙ КОМПЛЕКС ООО "СОЛИД-КАМА"
Location: Moscow, Khoroshevsky district
Total area: 8 500 m2
Construction period: 2004-2006
Completed works: construction.
ТАМОЖЕННО-СКЛАДСКОЙ ТЕРМИНАЛ ООО "ТСТ-ТРАНССЕРВИС"
Location: Pushkin District, Tarasovka
Total area: 65,000 m2
Construction period: 2004-2006
Completed work: customer functions, designing, construction.
Project features: Unique 18-meter monolithic columns were made; high-flat industrial floors were made for high- storage.
ПОЛИГРАФИЧЕСКИЙ КОМПЛЕКС ООО "ПЕРВЫЙ ПОЛИГРАФИЧЕСКИЙ КОМБИНАТ"
Location: Krasnogorsk district
Total area: 30,000 m2
Construction period: 2003-2005
Completed works: customer functions, designing, construction.
Project features: The most complicated technological foundations for printing manufaturing were constructed.
АДМИНИСТРАТИВНОЕ ЗДАНИЕ ЗАО "СЕРВИС ДЕЛОВОГО МИРА"
Location: Moscow, Khoroshevsky district
Total area: 6,000 m2
Construction period: 2002-2004
Completed works: designing, construction.
УЧЕБНО-МЕТОДИЧЕСКИЙ ЦЕНТР ФОНДА СОЦИАЛЬНОГО СТРАХОВАНИЯ РФ
Location: Odintsovo district
Total area: 56,000 m2
Construction period: 2010-2014
Completed works: customer functions, designing, construction.